348 infra projects show cost overruns of over Rs 3 lakh crore
For 650 projects, neither the year of commissioning nor the tentative gestation period has been reported. Out of 263 delayed projects, 66 projects have overall delay in the range of 1 to 12 months, 50 projects (13-24 months), 71 projects (25-60 months) and 76 projects (61 months and above), it added.