Aim to complete Barapullah Phase-3 flyover by December: Delhi PWD minister
The third phase of the Barapullah elevated corridor project was to connect South Delhi to East Delhi. This project, which was started seven years ago, has not been completed yet, despite tall claims and promises.
)
02:26 PM IST
The Delhi government is pushing to complete the long-delayed Barapullah Phase-3 flyover by December this year, Public Works Department (PWD) Minister Parvesh Verma announced on Monday during a visit to the project site.
Describing it as a major infrastructure initiative, Verma said work has picked up pace after delays caused by pending payments and administrative hurdles under the previous government.
"This is a very big project. The company handling the construction had raised concerns about non-payment. We have cleared those dues, and you can see the progress -- last time we visited, work was stalled, but now the bridge is almost ready," Verma told reporters.
"We're actively following up on the approvals needed to shift the trees. The previous government neglected this issue and failed to release contractor payments, causing major delays. We are now working to ensure the remaining work is completed at the earliest," Verma added.
The third phase of the Barapullah elevated corridor project was to connect South Delhi to East Delhi. This project, which was started seven years ago, has not been completed yet, despite tall claims and promises. Efforts are also being made to increase the length of the Barapullah flyover through this project. The total length of the phase 1, 2 and 3 corridors of Barapullah flyover is 9.5 km.
The Barapullah Phase-3 corridor aims to provide signal-free travel between east Delhi's Mayur Vihar-I and AIIMS in south Delhi by linking the new flyover with the existing Barapullah stretch at Sarai Kale Khan.
Though 98 per cent of the construction has been completed, the remaining work is held up due to pending approvals from the forest department for the relocation of nearly 200 trees. The project, which began in 2015, was initially scheduled for completion in 2017.
Get Latest Business News, Stock Market Updates and Videos; Check your tax outgo through Income Tax Calculator and save money through our Personal Finance coverage. Check Business Breaking News Live on Zee Business Twitter and Facebook. Subscribe on YouTube.
RECOMMENDED STORIES
)
7 Stocks to buy for long term: Analysts recommend largecap, midcap stocks; Axis Bank, Ambuja Cements on the list
)
Top Performing Mid Cap Mutual Funds with Highest SIP Returns: Rs 25,000 monthly investment in No. 1 fund has grown to Rs 60.18 lakh in 7 years
)
Power of Rs 10,00,000 One-time Investment: How your Rs 10 lakh investment can turn into Rs 3 crore, Rs 4.47 crore, and Rs 6.63 crore in 30 years
)
8th Pay Commission Pension Calculations: How your Rs 20,200, Rs 25,250, Rs 34,000, and Rs 44,200 basic pension can be revised at 2.10-2.50 fitment factors (detailed charts)
)
SIP Calculation: Rs 14,000/month investment, how quickly can you generate over Rs 13 crore corpus? See calculations
)
8th CPC Salary Calculations: What can be revised basic pay for Grade Pay 1800, 2400, 2800 and 4200 employees at 1.92, 2.08 and 2.28 fitment factors?
)
Power of Rs 13,000 SIP: How many years will it take to generate Rs 9,00,00,000 corpus with just Rs 13,000 monthly investment?
)
Rs 30,00,000 Lump Sum Investment in Mutual Fund: In how many years can you create a corpus of Rs 1 crore, Rs 2 crore & Rs 3 crore at 12% annual return?
02:26 PM IST